Client

Start Date
June 2010
Completion Date
June 2017
Scope
Complete upgrade / replacement of the P&C and SCADA systems for three substations for the City of Red Deer.
Highlights
- Modernization of a 138kV to 25kV point of delivery substations.
- IEC61850 introduced, first in North America with Parallel Redundancy Protocol.
- Complete substation simulation during FAT – fully controllable mock-up including all breakers & MODs, automated bus transfer scheme and transformer LTC master follower scheme.
Challenges
- Implementation of IEC61850 which was the first in North America.
Services Utilized
- Engineering
- Base Electrical and Lighting layout
- Interior elevations
- Cable tray & fiber duct layout & details
- Grounding layout & details
- Bldg AC/DC distribution design drawings
- Lighting Contactor Panel design drawings
- E-room cable schedules
- Building alarm design drawings
- Fabrication of all P&C panels/relays (replacement)
- Installation
- Full commissioning